I-295 Project Status

As part of the Phase 1, the contractor will close Ramp D-2 (Northbound I-95 / I-295 to Northbound SR 141) from 4am to 6pm to complete lighting pole base installations. The following movements at the ramp will not be permitted.

  • Northbound I-95 / I-295 to Northbound SR 141

Expect delays during the work period.

Detour information for the closure of the ramps is provided below or as shown on the Detour Maps.

  • Detour – Ramp D-2 (Northbound I-95 / I-295 to Northbound SR 141)
  • For traffic normally accessing Northbound SR 141 from Northbound I-95 / I-295:
  • Detour route along Northbound I-95 / I-295 will have motorists will continue along northbound I-295, take ramp to Southbound US 13, take ramp onto northbound SR 141 arriving at northbound SR 141